Are Your Inventory Projections Accurate?
With increasing competition, product proliferation and innovation, as well as global supply chains with potentially long
lead times, managing inventory has become increasingly important.  Companies are instituting aggressive campaigns
to reduce inventory as a part of working capital.  However, many companies miss their goals.  Their teams create
unrealistic estimates of inventory and then fall short of these estimates.  What’s worse, those same teams have
trouble understanding and explaining the miss, and consequently confidence erodes in meeting inventory goals.  If
these inaccurate projections are plaguing your supply chain performance, then it is time to reevaluate the inventory
management process.

For a lot of companies, inventory projections are done independently or sometimes by personnel that don’t actually
control inventory levels.  In some cases, the projection is simply a best guess or perhaps a forecast based on
historical levels.  This leads to inaccuracy, because of an important fact:  
inventory is an outcome of other
functions
.  If we can understand and plan those functions, we can better manage inventory.

Simply put,
inventory is controlled by two types of material flows—Outbound and Inbound.  Outbound
material movements are customer shipments for finished goods (FG) and production usage for work in process (WIP)
and raw materials (RM).  Inbound flow are created by material creation or production (generally for WIP and FG) or by
material ordering and receipt (RM and some WIP and FG).  Interestingly enough, a company actually controls most of
these processes through material ordering and production.  And although customer shipments may not be controlled,
these are almost invariably forecasted and monitored by every business.

With this in mind,
inventory projections need to calculated, not forecasted.  For any material at any stage, for
each period of time, inventory should be calculated by this simple equation:

                                         Beginning Inventory – Demand + Supply = Ending Inventory

Again, demand can be comprised of multiple components, same with supply.  Ideally this calculation for future periods
should be made for
every material, so that a detailed rollup is available.  This projection is based on the inventory
drivers, not a rough estimate.  More importantly, when actual inventory is compared to projections, reasons for
success and failure can be easily pinpointed.  Inventory variances should be either because demand or supply did
not come in as expected (inventory accuracy is a potential third source of variance; inventory accuracy has other
available solutions).  Once the reason for variance is known, then supply chain personnel can correct the issues
driving the variance.  As a side benefit, the team will also understand the estimated accuracy for future inventory
projections.

Inventory projections can seem mystifying, but are relatively simple to do correctly.  There is complexity in tracking
FG, WIP and RM, but this level of detail is necessary for succinct inventory management.  Getting a handle on
inventory projections and variances is the first step to inventory reduction.